MAIN WORKS IN PROGRESS
  • Heating Furnace for the extrusion of forged convex cap nozzles
    (nuclear and chemical vessels)


    Main technical features: Confidential data

    Commissioning and start up: within November 2011.

  • Heat treatment furnace for pressure vessel shell rings.

    Main technical features:
    Max net weight: 350 t
    Max shell ring dimension
    diameter : 8700 mm
    height: 6000 mm
    thickness: 600 mm
    Max operating temperature: 1100 °C
    Uniformity of the forging temperature at 850°C: ±10 °C
    Uniformity of the forging temperature at 600°C: ±5 °C

    Commissioning and test runs: within April 2012.

  • Atmosphere separators and entry/exit section for Heating Furnace
    for the treatment of Silicon Not Oriented Steel Strip.


    Main technical features:
    Strip dimension
    max width: 1350 mm
    thickness: 0,2 – 1,5 mm
    Max line speed: 180 m/min.

    Commissioning and start-up: within April 2012.

  • Cotilia Peschiera Hydroelectric power plant revamping.

    Delivery: within April 2012.

  • Pilot plant for stabilization thermal treatment of refinery petroleum sludges to inert safe state

    Main technical features:

    Stabilization treatment foresees two stages:
    1. sludge gasification reactor with thermal recovery of syngas.

    2.inertization of greasy ashes coming out from
    reactor inside a plasma torch furnace.

    Commissioning and start-up: within September 2011






http://www.gruppotecnofin.it